Modernization at Boscov’s

Boscov’s Department Stores DC makes gains from new sortation, controls and software plus racked order processing area.


Modernization at Boscov’s

Boscov’s Department Stores

  • Location: Reading, Pa.
  • Size: 395,000 square feet, plus attached 85,000 square feet building for stock replenishment.
  • Products Handled: apparel, home goods, furniture, bedding, luggage, seasonal items.
  • Throughput: 270,000 cases per week outbound, in peak seasons.
  • Employees: 225, on average. Shifts: One 12-hour shift, five days a week.

Learn more about the Boscov distribution center. 


Boscov’s DC in Reading, Pa., has long made heavy use of advance ship notices (ASNs) to support crossdocking of goods for specific stores, with 86% of cartons having an ASN. Between store-specific labeling and the ASNs, many cartons, especially during peak seasons, flow right through the facility. During non-peak times, there is relatively less flow-through and more order processing activity.

Inbound shipments arrive at one of 35 receiving doors (1), mainly as floor-loaded cartons, though a small percentage of cartons arrive in containers, and a small volume of palletized goods are also received. The operation uses extendable conveyors that reach into the floor-loaded trailers to make unloading easier. These extendable conveyors flow into multiple inbound conveyors that move cartons to a pre-sorter system (2) toward the center of the facility, or to sorter C. Each have a scan tunnel immediately upstream from it to read labels and route goods accordingly.

Layout of the Boscov distribution center.

These two sorters will either route cartons to one of the outbound shipping sorters (3), or to one of the DC’s order processing areas it services, if order picking from stock, repacking or quality control steps are needed. The latest project upgraded one shoe sorter (sorter C) that can either route goods toward another shipping sorter route, or around to one of the value-added processing areas in the DC. This upgraded sorter, with additional diverts and conveyor path re-routing, added redundancy to outbound sortation, as well more flexibility for circulating cartons to order processing areas. The DC currently has 62 outbound shipping docks (4) along two sides of the main building.

The processing areas execute value-added services like taking goods out of cartons and repacking items as ready-to-wear products. They also handle quality control checks.

Two of these essential processing areas are located at the center of the main building, close to receiving, on two levels, one right over the other. On the ground level is Conventional Flat (6) where various services like repacking or labeling take place. A Ready-to-Wear processing area (5), located upstairs, provides item preparation, check-in, and processing onto the GOH system (garment on hanger).

The project added, using existing space, a new order processing area with racked storage, known as OP2 (7). This area provides easy access to goods that need to be held over the short to mid-term, using software to drive the order picking, as well as manually operated, narrow-aisle orderpickers for larger items or for pallet moves, and pick-to-cart for smaller items. Compared to dealing with goods stored in trailers, the reduced touches have significantly improved efficiencies in the DC. A pre-existing reserve storage area known as OP1 (8), remains in use and connected by conveyor to the other processes.

Nearly all the existing conveyor and sortation hardware, and all the five-sided scan tunnels, were replaced with new equipment, including programmable logic controllers (PLCs) and other key parts of the controls layer. A key addition was a new sawtooth merge (9) that brings together six lanes of goods coming from receiving and processing areas, to feed the new sorter C at a higher rate. The merge provides a pull system that allows upstream accumulation conveyor, feeding from the various areas, to operate without backing up the processing areas. The induct and sortation on sorter C operate with minimal gaps and are designed to handle a rate planned for several years in the future.

 

System suppliers


Article Topics

Automation
Conveyors
Crown Equipment
Honeywell
Order Fulfillment
Retail
Rockwell Automation
Zebra Technologies
   All topics

Crown Equipment News & Resources

Boscov’s Distribution Center: Speed regained in retail distribution
Lithium Transition: It’s all about the outcomes
Jumping on the narrow aisle trend
Your telematics data to-do list

Latest in Logistics

FTR’s Shippers Conditions Index shows modest growth
Trucking executives are set to anxiously welcome in New Year amid uncertainty regarding freight demand
ASCM’s top 10 supply chain trends highlight a year of intelligent transformation
Tariffs continue to cast a long shadow over freight markets heading into 2026
U.S.-bound imports see November declines, reports S&P Global Market Intelligence
FTR Trucking Conditions Index shows slight gain while remaining short of growth
AAR reports mixed U.S. carload and intermodal volumes, for week ending December 6
More Logistics

About the Author

Roberto Michel's avatar
Roberto Michel
Roberto Michel, senior editor for Modern, has covered supply chain management trends since 1996. He has been a contributor to Modern since early 2010s. Michel joined the staff full time in 2020, writing on a wide range of topics including warehouse-level software systems, robotics and lift trucks. He has worked on numerous ProMat and Modex show dailies over the years. Since mid-2024, he has authored Modern's System Report cover stories. You can reach him at: [email protected].
Follow Logistics Management on Facebook
Logistics Management on LinkedIn

Subscribe to Logistics Management Magazine

Subscribe today!
Not a subscriber? Sign up today!
Subscribe today. It's FREE.
Find out what the world's most innovative companies are doing to improve productivity in their plants and distribution centers.
Start your FREE subscription today.

December 2025 Logistics Management

December 1, 2025 · Persistent volatility, policy whiplash, and uneven demand left logistics managers feeling trapped in a loop - where every solution seemed temporary, and every forecast came with an asterisk. From tariffs and trucking to rail and ocean freight, the year's defining force was disruption itself

Latest Resources

The Warehouse Efficiency Playbook
Warehouse leaders are under pressure to move faster, scale smarter, and keep teams engaged, all while dealing with labor shortages and rising customer expectations.
Drive Agility and Resilience Across Your Supply Chain
November Edge Report: What’s shaping freight now
More resources

Latest Resources

The Warehouse Efficiency Playbook
The Warehouse Efficiency Playbook
Warehouse leaders are under pressure to move faster, scale smarter, and keep teams engaged, all while dealing with labor shortages and rising...
Drive Agility and Resilience Across Your Supply Chain
Drive Agility and Resilience Across Your Supply Chain
Today’s supply chains face nonstop disruption—from global tensions to climate events and labor shortages. Avoiding volatility isn’t an option,...

November Edge Report: What’s shaping freight now
November Edge Report: What’s shaping freight now
Stay informed and ready for what’s next with the November Edge Report from C.H. Robinson.
Worried About Supplier Risk? This Template Helps You Stay Ahead
Worried About Supplier Risk? This Template Helps You Stay Ahead
We all know how stressful it gets when a supplier issue catches you off guard - late delivery, a missed order, or...
Close the warehouse labor gap with overlooked talent pools
Close the warehouse labor gap with overlooked talent pools
The warehouse workforce has more than doubled between 2015 and 2025. However, the labor gap is still growing, with the U.S. deficit projected...